When Huel’s state-of-the-art UK facility needed a permanent, compliant segregation solution for its dry powder process area, there was no room for downtime. Westgate Global specified and installed a 1,000 m² Flexiwall tensioned fabric partition that met a Class B fire rating and strict food-safety hygiene standards over ten weekends, with production running throughout.
Contamination control for a food manufacturing plant
Huel has become one of the most recognized names in nutrition since launching in 2015. The food brand is built on the promise of manufacturing food that’s good for people and good for the planet. Living up to that promise means having high standards, with nutritionists, food scientists, and quality assurance teams signing off on exacting specifications for every batch. Hitting that bar consistently, at volume, takes serious manufacturing infrastructure.
To meet their goals, Huel opened a purpose-built manufacturing and distribution facility in Milton Keynes, UK, in 2024. From day one, the plant was engineered to meet the company’s zero-compromise approach to quality. Central to the design was a permanent physical barrier isolating the dry powder production zone from the rest of the warehouse, a must-have for meeting strict hygiene and food-safety requirements.
The enclosure installed by the original construction contractor fell short of fire-resistance requirements. Huel needed to act fast, and the replacement had to check three boxes at once: permanent, fully compliant, and installed without pausing production
A tensioned fabric wall built for industrial food environments
Westgate Global started with a full site audit, then specified Flexiwall, a tensioned fabric partition system engineered for large-scale industrial settings. The finished installation spanned roughly 10,800 square feet and achieved a Class B fire rating under the EN 13501-1 European reaction-to-fire standard, while also satisfying the hygiene demands of an active food production environment.

The team also built in a Fastflex rapid-action door sized for the high-reach forklifts moving through the space, so material flow never had to stop for the wall to go up.